Really appreciate, Arpit-san Using the Excel is very effective for the customer. I want to ask additional thing to you. In the case of " RESOURCE ASSIGN_OBJECT(VAR 3D(UFV("Task Location")==$0.NAME)) " script, 3D objects are included in the created task as follows. If possible, we want to add the children task under the parent task. If so, what parameters in script we should add? (First of all, it is possible to do the above via SYNCHRO Script technologically?) If you need more information, please let me knwo. Best Regards Satoshi Matsuura
↧