I would like to know how to split one schedule task (same task) to appear on different time during the project (ex. scaffolding on week 14, then break until week 29 where they work for 10 days with casting, and then in break until week 45 where they remove scaffolding)? Shorter period is also applicable in my projects. Looking forward to some ideas. Thank you in advance. //Thambo
↧