Has anyone developed a script that will automatically add child tasks to activities based on keywords? For Example: Schedule gets to a detail level of "F/R/P SOG Level 1" or "F/R/P Elevated Slab Level 2" The script would identify activities with the keyword "F/R/P" The script would then automatically add the following activities as child tasks and link them as a chain: Shoring/Forming Reinforce Pour Strip/Shoring Removal Cure It would then Link "Shoring/Forming" to the summary activities predecessors and it would link "Cure" to the Successors of the summary task A bonus to this would be reassigning resources from the summary activity to the child activities with particular appearance profiles. Not sure if this is even possible but I figured I'd ask. Thank you, Preston Williams
↧