Hello, We are trying to compare the Resource Usage of the actual schedule with a baselined schedule with the Resource Usage Graphs in Synchro 4D Pro. I believe there is no functionality in Synchro 4D Pro that allows us to do this. We could show the Resource Usage of the actual plan, make a print or printscreen, then restore the baseline and make a print or printscreen. Alternatively we could export the original and baseline data to Excel and visualise both the graphs in Excel or Power BI, but we would like an easier and faster workflow. All suggestions are welcome. Best regards, Stephan Klotz
↧