Product(s): ConstructSim Work Package Server Version(s): N\A Environment: N\A Area: N/A Subarea: N\A I want to change the way the Productivity Factor (PF) of my Work Package is calculated. Background By default the Productivity Factor of a Work Package is calculated using the equation Actual Hrs/Earned Hrs. I want to change that to calculate it as Earned Hrs/Actual Hrs Steps to Accomplish Open eB Director Browse to the Documents>WPS Settings>Project Template and expand the Files panel Right Click on the 'wps_Settings.xml' file and chose> Check Out Edit wps_settings.xml the file in the checkout location and change the "Productivity Factor" setting Ø From: Save the edited file and check it back in through eB Director
↧