Wiki Page: Status update on a 4D collaboration project

$
0
0
Getting started To get started, review the following content: Capture progress by model and why Set up a 4D collaboration project in SYNCHRO Control Prepare data in SYNCHRO 4D Pro for Status Update in SYNCHRO Field Status Update - tasks Menu option "Status Update" will be visible when app user has tasks for given project. It then can be used to perform statusing. Tasks are listed for active user based on Resource Groups assigned to them. User is shown Tasks that have Resources assigned via their Resource Groups. Tasks are filtered based on their planned start and planned finish dates. Default filter of "This week" will show tasks that are active ("planned") for any day in those 7 days.