Forum Post: RE: Critical path and Tower Crane

$
0
0
Hi Hamed, Hammock tasks are excluded from Critical Path calculations, so creating the Crane task with T ask Type as Long Hammock and having a predecessor and successor logic links defining the duration, should serve your purpose.