Hi, I had 2 different SP file. when one SP file was added into another, the combined SP file had 1 schedule in it and one from the imported SP file.(which is inside the SP file). i exported the combined xml file and imported in P6. and when i synchronized the same xml of p6 into Synchro. many 3D resource assignment were missing. tried multiple setting for snychronize, integrate and consolidate for taks link resource still fail please advise. Thanks
↧