Hi Samuel, SYNCHRO 4D Pro has direct integration with the native PP file format, however, you would need Asta to be installed on the same system as SYNCHRO. If the first import was done through File > Import > Asta Powerproject , then you can synchronize any updates by going to External Data > Right-Click on ASTA schedule > Synchronize . There is no other easy way to seamlessly update the revised schedule.
↧