Hi Muhammad, There are a few things to keep in mind when working with P6 Cost in SYNCHRO - SYNCHRO does allow costs to be directly added to a summary Task but aggregates them up from the leaf/child tasks. Please ensure all your P6 cost data is added to leaf tasks. In P6, ensure that Resource > Units & Price > Effective Date is set before the start of the project. SYNCHRO cost rate is treated as 0 before the effective date. Ensure all your dates are correct as there can be discrepancies due to compatibility with Task types. For example, SYNCHRO does not support Level of Effort tasks, and the logic links/duration may be incorrect, thus affecting the cost. Make sure you have updated to the latest SYNCHRO 4D Pro v6.5.
↧