Hi HoSang, I believe SYNCHRO uses standard EAC calculations, as explained in this article . Planned Tasks, EAC = AC + Bottom-up ETC Finished Tasks, EAC =BAC/Cumulative CPI For Started Tasks, EAC = AC + (BAC - EV) or EAC = AC + [BAC - EV / (Cumulative CPI x Cumulative SPI)]
↧