Hi everyone I have a problem: I have 2 versions of synchro scheduler programme - 1 is initial old and 1 is the updated with additional tasks and updated dates. I want to use the dates from the old programme as my baseline for the updated one. I've created the baseline in my old version. However, I can't figure out how to import it in the updated version of the project. Can someone please provide a step by step solution? Cheers guys
↧