Hi Tornado, Performance is mostly determined by your computer specs and the no. of Activities you are synchronizing from P6. How much time does it take to synchronize, and for how many Tasks? For Total Float values, you can expose required columns by right-clicking on the Task List header > Customize Columns. Make sure to Compute Critical Path to populate these columns. It's hard to identify the reason for the discrepancies without reviewing the schedule. I would recommend reaching out to SYNCHRO Support for further investigation. One of the more common issues arises due to mismatched Task Types . SYNCHRO does not support Level of Effort tasks, and the logic links/duration may be incorrect. Also, make s ure you have updated to the latest SYNCHRO 4D Pro v6.5. Not really sure what u mean by integer values, but you can change the Duration format from under Options - Do you mean you do not want the units (d,h,etc) at all?
↧