Is it possible to simulate % Complete for planned tasks, according to Focus Time? The idea is to prepare a simulation for planned dates only and to show, how the tasks progress, while the Focus Time is advancing further. Focus Time would be treated as Data Date, and Progress Type would be automatic. The value would be (Duration at Focus time)/(Planned Duration)*100%, i.e. [(Planned Finish - Focus Time)/( Planned Finish - Planned Start)]*100% That would be a dynamic value, displayed f.ex. on Gant Chart: Whatever is behind Focus time, it is completed changes coulur, and % changes as the Focus Time moves forward.
↧