Hi Daria, Unfortunately, this is not possible with SYNCHRO 4D. There is no way to treat Focus Time as Data date, and will not be able to automatically use any formula/script to get the % complete either. All these calculations will have to be done manually. The maximum you can do is create a Constant for FocusTime , update the date value for subsequent progress updates which are again run manually using the formulas you mentioned. Is this feature available with any third-party scheduling software?
↧