Forum Post: RE: Adding child tasks to a task that has already begun in the schedule

$
0
0
Thanks Arpit, the question raised by Dennis also appeared in our discussion: - When some task has status Finished, however, you like to add the details - the child tasks, as it easy to do in MS Project, but not possible in Synchro. The reason is obvious: When the work has status "Finished", it is not only marked as Completed, but also usually is PAID, and it is reflected in many accounting papers, which has legal status. One can add detailed description either with way around pointed in post Arpit, or by creation NEW task, however, to do it with good understanding if it is completed, or should be made.