"Manage forms"?">Forum Post: RE: Why isn't it possible to delete erroneous/superfluous forms...
absolutely agree!!! there is no logic in how the bindings are created and used among the forms, so often you end up creating duplicate properties you cannot remove
View ArticleForum Post: RE: Synchro 4D Pro 6.4 Issues
I feel you there Mike, this version looks way more sluggish than 6.3, crashes quite often. I have also noticed the 3D window sometimes fails to render. the only way to move forward is close and restart...
View ArticleForum Post: RE: Adding child tasks to a task that has already begun in the...
Thanks Arpit, the question raised by Dennis also appeared in our discussion: - When some task has status Finished, however, you like to add the details - the child tasks, as it easy to do in MS...
View ArticleForum Post: HELP. Synchro 4d Pro, Synchro Scheduler. Synchro Construction...
Help. What is the difference between the 3 softwares, Synchro 4d Pro, Synchro Scheduler, Synchro Construction Modeler. Do I need to install the three softwares for creating project managements files...
View ArticleForum Post: Coffee Corner: SYNCHRO – Progress Tracking and Field Statusing...
Title : Coffee Corner: SYNCHRO – Progress Tracking and Field Statusing Using Resource Statuses Presenter : Kerry Newbanks , Industry Solution Advisor, Construction Operations, Bentley Systems Inc,...
View ArticleComment on SYNCHRO SCRIPT
Hi Indrawan Wijaya We have created a new material resource and have a 3D filter, looking for a script to assign all elements in 3D filter to the new resource. Both having the same name .
View ArticleComment on SYNCHRO SCRIPT
Also assign the resource Directly to the Task from the 3D filter which also has the same name
View ArticleForum Post: Script assign Resource from 3D filter to Resource or Resource Group
We have created a new material Resource/New Resource Group and have a 3D filter both having same name, we are looking for script help on the following ways; 1) Looking for a script to assign all...
View ArticleForum Post: RE: What is the main difference between, or benefit of, using...
Hi Sophie, All the functionality for inspections is there now, other than the auto generated forms per the WBS. The WBS tree is configurable and forms are configurable. It's just a little more "manual"...
View ArticleForum Post: RE: Synchro 4D Pro 6.4 Issues
Hello Mike, Our support team have been trying to contact you about your crash issues. Ticket number: 207490 Can you please ensure that your graphics adapter drivers are fully updated? We can see from...
View ArticleWiki Page: Known issues - SYNCHRO Field
Status update: "Indefinite" Sync spinner when syncing status changes Status update: Statuses updated from non-Default category in 4D Pro do not color elements properly in Field
View ArticleWiki Page: SYNCHRO Field
SYNCHRO Field is the solution to managing projects from the construction job site. By capturing accurate, real-time data with highly efficient geo-located map and weather services, the entire team will...
View ArticleForum Post: RE: Script assign Resource from 3D filter to Resource or Resource...
Hi Zahid, There's no way of automatically selecting and processing all the 3D Objects in a 3D Filter using a script. You will have to manually select them by right-clicking on the filter > Select...
View ArticleForum Post: RE: Script assign Resource from 3D filter to Resource or Resource...
Thank you for the detailed explanation Arpit
View ArticleForum Post: Calculate task user field from resource user fields with a...
I am trying to create a task user field thats sums up the value of a user field for resources assigned to a task, but only for resources that have a a specific value in a different user field. For...
View ArticleForum Post: RE: HELP. Synchro 4d Pro, Synchro Scheduler. Synchro Construction...
install only Synchro Pro 4D. the others are pretty useless.
View ArticleForum Post: RE: Calculate task user field from resource user fields with a...
hi Connor, You can try use this script: TASK (SELECTED ) ASSIGN_UF ("Total Volume" , FLOAT, SUM(RESOURCE (UFV(" Material ")==" Concrete ").UFV ("Volume") ) Hope this help. Best regards, Indrawan
View ArticleForum Post: the 3D model in Control is not helpful
This is going to be a rant in a feedback disguise: what is the point of having a 3D model when I cannot import any information besides a useless element id? when I organize my 3D model object into...