Hi Trevor- Hope you had a nice weekend. Thanks for the screenshot. In Pro the budgeted direct cost SUB for the selected task is $71,456, which matches what's in P6. Is this the expected result? If you assign expenses to activities in P6, they will come into Pro as budgeted direct cost items. It should work the other way around as well, i.e. setting it up in Pro and export to P6. In this case the following P6 settings may be helpful if you are trying to bring data back to P6. Without having the P6 XML and the Pro SP files I could only guess what you are trying to achieve. Please feel free to send me the files for investigation if you think this is an issue of Pro. I am happy to have a look. You can email directly to synchrosupport@bentley.com or if you think this is a product defect you can go to the top of the page and click idea, to submit an idea for SYNCHRO Pro.
↧