Forum Post: RE: Sorting columns in simulation
Hello- In this case you will have to build activities for this detailed simulation. Unless "Left to Right" growth simulation is acceptable which will allow the piles to be installed one by one, I...
View ArticleForum Post: RE: exporting eva chart and gantt animation
Hi Amalia- From experience and without actually seeing any screenshot or your file, I believe you will need to size the EVA chart a little so the curve is positioned within the EVA window in the User...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
Hi Trevor- Hope you had a nice weekend. Thanks for the screenshot. In Pro the budgeted direct cost SUB for the selected task is $71,456, which matches what's in P6. Is this the expected result? If you...
View ArticleForum Post: RE: Assign object to several tasks
Hello- As i understand you'd like to use the same object to visualize several activities as some of the activities may be non-modeled. Here is how you can achieve this: - you will need to set up...
View ArticleForum Post: RE: Sorting columns in simulation
Hello Chen, one of my customer wants to use this detailed simulation. He asked me to use one by one columnswith this simulation tecnique. He has used Asta4d. This simulation technique can be used in...
View ArticleForum Post: RE: Sorting columns in simulation
Hi- please submit an idea using one of the buttons on the top of the web page. If you can provide more information and if your client is willing to, please ask him to provide some screenshots and...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
communities.bentley.com/.../LNTP.zip Thanks Jacqueline, I think you are misunderstanding me. I have attached the two files. If you take the P6 file and and try to import it into Synchro, the costs...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
Trevor- Forgot to ask, which version of Pro are you using? It can be found in Help> About.
View ArticleWiki Page: SYNCHRO Pro/ Scheduler/ Open Viewer 2019.2 (v.6.2.1.3) Release
SYNCHRO Pro SYNCHRO Scheduler SYNCHRO Open Viewer SYNCHRO Plug-ins Update is available here Quick Links & Highlight Video Visit Software Downloads in the Bentley CONNECTION Center. Look for brand...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
Hi Trevor- This looks unusual to me that the unit rate is set to $0 for all resources but the budgeted costs are still calculated in P6. Can you find out from whoever created this P6 schedule whether...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
Yep, I set the flag calculate cost from units to off, as I don't have a set rate for each resource, nor can one really be calculated. This setting is actually shown on the first screenshot on my first...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
Hi Trevor- When you said that you "flag calculate cost from units to off" and you didn't have the rate set up for the resources. I have the following questions and would like to know your answers to my...
View ArticleForum Post: RE: I am having trouble synchronizing costs between P6 and...
Hi Jacqueline, 1) Can you let me know how budgeted costs for resources were populated? These were calculated via the estimate, and imported into P6 via Excel. 3) If the budgeted costs for resources are...
View ArticleForum Post: Script for creating a Resource group from Resources already...
Is it possible to have an script to create automatically Resource groups from the resouces already linked to a task in an individual way? Thanks for your help!
View ArticleForum Post: RE: Revit Export Error
Yes I use latest plug in. I know it is some settings issue or other elements corruption in Revit. Because some files works well.
View ArticleForum Post: RE: Revit Export Error
By the way the latest release is 6.2.2.0 which was released two weeks ago. Here is how you can troubleshoot: 1. Uncheck shared coordinates, then export the two spx. then import into Pro. Do they look...
View ArticleForum Post: RE: Script for creating a Resource group from Resources already...
Hi Maria- do you want to just associate resources to resource groups by some common UFVs? Or you are looking to associate R to RGs and in addition assign the RGs to Tasks? You can assign Rs to RGs...
View ArticleForum Post: Recalculate Values in User Fields
How do I set the function "Recalculate Values" in User Fields to be automatic calculated, in stead clicking everytime to update the field? Thank you very much.
View Article